Development
Mercialys is upgrading its Shop•Park sites to strengthen their position in their catchment areas. Its projects fall into three categories: the restructuring of existing sites, their extension, and the development of new Shop•Park sites on land it controls.
Project capex amounts to around €100 million over 2026-2028, followed by €200 million over 2029-2031. Each project targets an internal rate of return of at least 10% and can be suspended or phased depending on market conditions.
The six ongoing projects, in Brest, Niort, Marseille Plan de Campagne, Grenoble, Saint-André (Reunion Island) and Dijon, will together generate more than €10 million in additional rents on a full-year basis once delivered.
Status as of October 15, 2026.
Brest (29)

Following the departure of Géant Casino, the former hypermarket at the Phare de l’Europe Shop•Park has been fully relet: Leclerc (hypermarket on an optimized surface area, toys and drugstore), Grand Frais and Action. The first phase, delivered in 14 months and on budget, opened on December 4, 2025; footfall at the site rose by around 50% in December 2025. Delivery of all units and the commencement of the new rents are expected in 2027.
Niort (79)
The former Géant Casino hypermarket is being restructured: Lidl, New Yorker, Normal and Monky have signed leases there, and 90% of the space had been relet as of February 2026. Mercialys expects this to increase footfall by at least 30%. Full delivery and the commencement of the new rents are expected in 2027.
Marseille Plan de Campagne (13)
Restructuring of the largest hypermarket in the portfolio (22,000 sq.m): creation of a “right-sized” 12,000 sq.m food store, a 7,000 sq.m Nikito leisure complex, a mid-size unit and several small stores. The project is around 80% pre-let, with delivery expected in mid-2027 and estimated value creation of 10%.
Grenoble (38)

Restructuring and extension of the site’s covered section: the enclosed mall is making way for new mid-size units and more efficient retail formats, with a complete renovation of the circulation flows and signage and a “gourmet promenade”. Launched in mid-2026 and 90% pre-let, the works are due to be delivered in the second quarter of 2027; the project will generate around 20% of additional net rent.
Saint-André, Reunion Island (974)

Development of a 15,000 sq.m Shop•Park, including 11,000 sq.m of retail space, on land reserves owned by Mercialys, in a densely populated area with limited competition in the north-east of the island. Launched in mid-2026, the works are due to be delivered in the second half of 2027; pre-letting exceeds 90% and the expected yield is above 9%.
Dijon (21)
Redevelopment of the Dijon-Chenôve site. Lidl has signed and pre-letting is already close to 50%, with delivery scheduled for the fourth quarter of 2028.
Mercialys’ Asset Management and Works teams oversee each project from diagnosis to delivery, based on an analysis of the commercial, technical and economic challenges of each site. Projects are activated in a disciplined manner, in line with the development plan, and can be suspended or phased depending on market conditions.
Mercialys favors the restructuring of existing buildings and developments on land that is already sealed, for example by reducing the surface area of a hypermarket to create several stores. It is thus aligned with the national “net zero artificialization” objective.
Other projects are to be launched from 2027-2028, notably in Angers, Lanester, Quimper and Saint-Denis (93), followed, over the longer term, by Ferney-Voltaire, in the Geneva area.
Angers (49)

A 16,000 sq.m land bank adjacent to the Shop•Park was acquired in 2025. It offers development potential of around 25,000 sq.m, including nearly 15,000 sq.m of retail, foodservice and leisure space, within a mixed-use district that also includes residential and office units.
Ferney-Voltaire (01)

A mixed-use project of around 17,000 sq.m, co-developed in a cross-border area between France and Switzerland; the preliminary sales agreement for the land was signed at end-2025 and the opening is scheduled for 2029.